Graphic: |
Arrived 16:11
A series of tests were carried out to determine and reduce Kr signal noise
The fast data was acquired for later analysis (logged as s7.020610):
- Battery pack ( 1.61v ) to AMP-9 - Good ~ 8035
- Battery pack to serial A/D - Good ~ 16065
- Kr 1394 installed (head in zip-log bag); wired directly to A/D (lots of
GOES noise)
17:00 disconnected the grey cable from Kr box and reconnected using
red cable (better shielding?)
17:05 removed plastic bag covering Kr head
- connected via front panel
Turned off station and re-did GOES shielding (twisted wires vs. clip leads to
ground, shielded GOES transmitter power as well). Noise now ~80,
A crudely-annotated plot of the above data is attached.
Conclusion: most of the "noise" seen on this station was still GOES
interference. I've significantly reduced it, but it is still present.
Time will tell if 1394 behaves better at this station than its former location
at s9. It checks out okay in the lab (13mA, 1.7V in dry air -- even
better than 1392 that just came back from Campbell) and I've just replaced
the 4-pin connector which had a small amount of white corrosion. Nevertheless,
I don't have much confidence that the connector change will fix the low-noise
problem.
Changed station configuration to use kry1394s.dat calibration file.
Departed 17:38
231: Site_visit, Site 8, Mon 10-Jun-2002 18:50:10 CDT, Site 8 visit
Arrived 15:45
Entered the correct coefficients for Kr 1391
Departed 15:50
230: Site_visit, Site 9, Mon 10-Jun-2002 18:45:20 CDT, Site 9 visit
Arrived 14:03
14:08 lowered mast
14:12 Kr 1492, both electronics and head remounted with path vertical
14:20 cleaned Kr
Changed power supply, VI-Taiwan -> VI 03/02-3
New configuration loaded
15:00 mast erected
Departed 15:14
229: Site_visit, Site 8, Sun 09-Jun-2002 18:55:29 CDT, Site 8 visit
Arrived 15:41
CO2 cal gas pressures. Note the pressures are only decreasing very slowly.
8/4 1940/8
8/1 capped
8/3 2090/8.3
355.8 1930/8.7
N2 2260/4.5
Set GOES transmission time by GPS. Was 4 sec off before correcting.
Dropped mast and mounted the three Kr heads below sonic.
To test the kryptons, we first mounted each of the 3 krypton boxes (by
climbing). Then, we dropped the tower and mounted all 3 Kr heads near the
sonic. We raised the mast and took more data through various boxes. Finally,
we dropped the mast to recover the 1393 & 1394 heads and raised the mast again.
Data were viewed locally using "fastsave" (after waiting 7-9 min :( )
The various combinations:
Head Box h2o w'h2o' h2o'h2o'
1391 1391 17.51 0.022 0.024
1391 1393 18.78 0.034 0.043
1391 1394 19.69 0.028 0.087
1393 1391 19.33 0.046 0.080
1394 1391 19.83 0.026 0.068
1394 1393 19.73 0.016 0.025
1393 1393 19.03 0.018 0.032
Done at 17:10
What I was expecting was near 0 w'h2o' using either 1393,1394 head or their
boxes. These results don't make sense -- perhaps we got to this site too
late to have good fluxes.
To work with these data further, I swapped SDR 5 -> 2.
Final mast erection at 17:23
Departed at 17:30
228: Site_visit, Site 7, Sun 09-Jun-2002 18:52:40 CDT, Site 7 visit
Arrived 14:12
Set GOES transmission time.
Exchanged serializer and examined noise:
Didn't have a working CSAT-1 serializer in the spare box :(, also the A/D
from the one CSAT-1 spare didn't work with the CSAT-1 CPU in the box.
Thus, changed to a configuration with the old CSAT-1 CPU and the A/D from
the UW-1 that we removed from s9 yesterday. The reference voltages were
nearly the same -- the CPU is -88 and the A/D is -86. I left it this way.
I used "fastsave" to examine the data, expecting a good result to be a large
reduction in h2o'h2o'.
h2o w'h2o' h2o'h2o'
17.82 0.029 0.145 before changes; obviously bad
17.91 0.023 0.199 "
18.24 0.023 0.028 change to -86 A/D; (short fastsave)
18.02 0.012 0.264 " (normal length fastsave)
18.03 -0.001 0.336 "; reseated all connectors on EVE and also
changed to spare Krypton signal cable
Obviously, none of these changes improved matters. I went back to the normal
cabling, though I left the -86 A/D board in place.
The only thing I can think of next is to work on the front panel itself!
Removed Kr 1393 for transport to station 8 for tests
Depart 15:21
227: Site_visit, Site 9, Sun 09-Jun-2002 18:47:00 CDT, Site 9 visit
Arrived 12:19
12:34 dropped mast
12:37 Disconnected Kr 1394 box and 1394 head to transport to station 8 for tests
!2:52 mast re-erected
13:00 K&Z sw.in had been erratic. Removed rad shield and wiggled intermediate
connector. This seems to have fixed the problem
GOES transmission time set according to GPS.
Departed 13:02
223: Site_visit, Site 7, Sat 08-Jun-2002 23:22:32 CDT, Site 7 visit
[A series of visits to isolate problem with krypton fluxes;
back to s7 to install s8's krypton]
Arrive: 1745
- installed kypton 1393 box and head
Depart: 1757
NOTE: Didn't change calibration files -- station is still using 1391
calibrations (but good enough for these tests?)
222: Site_visit, Site 9, Sat 08-Jun-2002 23:19:25 CDT, Site 9 visit
[A series of visits to isolate problem with krypton fluxes;
s9 visit to try another serializer; also change CR10 power; also calibrate PIR]
Arrive: ~1530 (walked in)
- clean radiometers; attempted shading tests 2x 60s each, but mostly cloudy
captured to s9l.020608
- install new serializer
- CR10 powered by standalone battery -- FINALLY DONE WITH THIS TASK!
- copied /card
Depart: 1620 (flat tire on the way out of the ranch :( )
221: Site_visit, Site 8, Sat 08-Jun-2002 23:16:07 CDT, Site 8 visit
[A series of visits to isolate problem with krypton fluxes;
s8 visit to swap kryptons; also calibrate PIR]
Arrive: 1402
- pressure line not connected at bottom of EVE box -- reattached
- dropped mast at 1410
- exchanged krypton box and head (1393 removed, 1391 from s7 installed)
- cleaned krypton at 1430 (150 -> 180mV)
- clean radiometers; shading tests 1410-1420, not clear sky
captured to s8l.020608
- raised mast 1435
- N2 2380/4.0
- SDR 2 -> 5
- copied /card
Depart: 1453
NOTE: Forgot to change krypton calibration file -- station is still using
1393 coefficients (but good enough for this series of tests?)
220: Site_visit, Site 7, Sat 08-Jun-2002 23:11:47 CDT, Site 7 visit
[A series of visits to isolate problem with krypton fluxes;
s7 visit to remove krypton; also change CR10 power; also calibrate PIR]
Arrive: 1311
- clean radiometers; start shading tests, though scattered clouds, 2x 60s each
captured to s7l.020608
- removed krypton 1391 at 1320
- moved GOES antenna back from SE to SW tripod leg (where we had put it during
the GOES interference tests a while ago)
- CR10 power to standalone battery
- copied /card
Depart: 1340
215: Site_visit, Site 6, Fri 07-Jun-2002 21:52:30 CDT, Site 6 visit
Arrive: 1741
[ongoing check of radiometers]
- radiometers cleaned at 1750, dessicant okay
- converted CR10 to fast mode; 0,1,0,0,0 coefs; collected data to s6l.020607
(had to direct-connect to CR10, sites 4&5 I did through EVE "talk")
at 1654; shaded 2x 1min each
- converted CR10 back to normal mode at 1758
Depart: 1802
214: Site_visit, Site 5, Fri 07-Jun-2002 21:50:36 CDT, Site 5 visit
Arrive: 1649
[ongoing check of radiometers]
- radiometers cleaned at 1652, dessicant okay
- converted CR10 to fast mode; 0,1,0,0,0 coefs; collected data to s5l.020607
at 1654; shaded 2x 1min each
- converted CR10 back to normal mode at 1703
Depart: 1703
213: Site_visit, Site 4, Fri 07-Jun-2002 21:43:33 CDT, Site 4 visit
Arrive: 1520
[check of bad krypton data on 6/6; ongoing check of radiometers]
- removed krypton head at 1525 to attempt to fix bad coax connector -- broke it
- hard wired connector to electronics! (Will make service/packing a bit
awkward.)
- radiometers cleaned at 1620, dessicant okay
- converted CR10 to fast mode; 0,1,0,0,0 coefs; collected data to s4l.020607
- converted CR10 back to normal mode
Depart: 1640
212: Site_visit, Site 3, Fri 07-Jun-2002 21:32:18 CDT, Site 3 visit
Arrive: 0956
[last station to "box" krypton electronics; ongoing conversion of CR10 power;
ongoing radiometer checks]
- cleaned krypton (pre: 250mV, post: 300mV) at 1002
- krypton box removed and opened -- no significant corrosion; still cleaned
a bit with Q-tip; reassembled
- mounted krypton in plastic box and reconnected at 1010
- changed CR10 to radiation calibration mode (all of these involve changing
the coefficients for Tdome&Tcase to 0,1,0,0,0)
- cleaned radiometers
- series of sun shading of PSP & PIR; captured to s3l.020607; finished at 1045
- change CR10 to separate power
- reset CR10 to normal operation
- downloaded /card
- checked through all channels
Depart: 1050
211: Site_visit, Site 1, Fri 07-Jun-2002 21:27:36 CDT, Site 1 visit
Arrive: 0838
[reinstalled soil profile wiring]
- CR10 had been running the radiation calibration code since we left yesterday,
though I thought I had changed it.
- Checked CO2 cal gases at 0848:
1/1: 1930/6.2
1/2: 1730/6.0
1/3: 1890/6.1
1/4: 1890/6.9
N2: 1700/6.2
- Reinstalled soil profile wiring
- Restarted normal program (*4 99 = 0)
Depart: 0917
210: Site_visit, Site 2, Thu 06-Jun-2002 21:23:46 CDT, Site 2 visit
Arrived 18:09
[ongoing boxing of krypton electronics; ongoing radiometer calibration]
Radiometer descicant LW.in OK, SW.in ?,spider persistant on LW.in. Cleaned domes
18:12 Kr disconnected. Box opened and was found to be sparkling clean without
any corrosion. Box mounted in plastic box
18:30 - 18:50 sun shadow patch test done on radiometers. Used 30s, 10s and 60 s
The logger was changed to fast data mode and later changed back to normal mode
Captured file s2l.020606
Card transfered.
!8:59 Kr windows cleaned.
A student, Jennifer? of Purdue was setting up a total column water GPS
Departed at 19:09
209: Site_visit, Site 1, Thu 06-Jun-2002 21:03:09 CDT, Site 1 visit
Arrived 14:44
[ongoing boxing of krypton electronics; fix of soil profile 5; start radiometer
calibrations]
All ventilator fans operating except LW.out. Power disconnected for vent fans
Gas cylinders fro the north:
1/1 2030 psi/5.5 psi
1/2 1850 psi/5.5 psi
1/3 2000 psi/ 6.0 psi
415.7 ppm 2000 psi/ 5.0 psi
Nitrogen 1850 psi/ 6.0 psi
Capped N2
Another capped cylinder of N2 was laying out of the array.
14:55 opened Kr electronics box: no corrosion. Remounted inside plastic box
on sonic side of the mast.
15:33 SDR 3 -> 6
Checked power from chem shelter: 12.23 volt
15:38 cleaned all radiometers, they appeared to have been OK
15:41 cleaned Kr windows
From 16:00 to 17:15 investigated the problem of the bad/missing data for the
profile 5 = P3 . Eventually discoverd bad corrosion in male connector at
logger. All three connectors had corrosion and the wiring was removed for
cleaning this evening at the motel.
From 17:15 to 17:35, the sun block by disc was done for the radiometers.
The logger was set to allow fast data to be collected. Found during call
to Steve Semmer that Tdome and Tcase were scaled incorrectly. Decided to
take data with just voltage output from these by changing all coefficients
to 0,1,0,0,0. Captured to s1l.020606
After the test the logger was programmed to its normal mode. [PS: WRONG!?]
Checked that clamp holding mast was secure.
Depart 17:44
208: Site_visit, Site 4, Thu 06-Jun-2002 20:53:12 CDT, Site 4 visit
Arrived 9:49
Logger already wired to an extra separate battery. This battery was recovered
and the logger was wired to the third PAM battery
A jury-rigged one screw mount, within the plastic box was made for the Kr. This involved rotating the Kr mounting block so the box is on the sonic side of the
mast. The small coax connector of the Kr 1390 electronics needed to be reseated.
Copied card
Depart 10:37
207: Site_visit, Site 5, Thu 06-Jun-2002 20:47:24 CDT, Site 5 visit
Arrived 9:15
Dropped mast, installed refurbished Kr in plastic box. Reinstalled head.
Rewired logger to third battery, PAM now has two batteries on the solar power.
Reconnected solar panels,
Copied card
Depart 9:40
206: Site_visit, Site 6, Thu 06-Jun-2002 20:42:46 CDT, Site 6 visit
Arrived 7:55, installed refurbished Kr 1397 on mast in plastic box
Connected CR10 to the independant third battery. PAM now has only two batteries
on solar power.
Copied card, checked EVE output.
Departed 8:22
203: Site_visit, Site 4, Thu 06-Jun-2002 11:02:31 CDT, Site 4 visit
[another log of this visit written by Tony]
Visit to reinstall krypton boxes after all that Tony brought back to the lab
yesterday passed inspection and to hang them in plasic boxes. This to be
done before a King Air PBL mission today over the Central legs.
- drove in (only wet around oil pumps)
- arrive 0949
- moved clamp, installed plastic box and krypton electronics by climbing
- copied /card
- switched CR10 from 4th battery to 3rd battery, disconnected 3rd from 2nd,
removed 4th battery (with controller/monitor)
- checked krypton signal -- was low, reseated connector -- was 30-13000mV,
knew that this meant bad signal (coax) cable/connector problem, but that
connector inside box checked out okay yesterday. Deduced that the problem
was the coax cable, played with cable, now 600mV. THIS CABLE PROBABLY
SHOULD BE REBUILT. S/N 1390.
- depart 1037
202: Site_visit, Site 5, Thu 06-Jun-2002 10:59:39 CDT, Site 5 visit
[another log of this visit written later by Tony]
Visit to reinstall krypton boxes after all that Tony brought back to the lab
yesterday passed inspection and to hang them in plasic boxes. This to be
done before a King Air PBL mission today over the Central legs.
- drove in (not too muddy)
- arrive ~0915
- dropped mast almost immediately
- reconnected solar panel
- reinstalled krypton head; installed plastic box and krypton electronics
- rewired CR10x power
- copied /card
- raised mast
- moved 3rd batter to rad stand
- depart 0940
201: Site_visit, Site 6, Thu 06-Jun-2002 10:55:48 CDT, Site 6 visit
[another log of this visit later written by Tony]
Visit to reinstall krypton boxes after all that Tony brought back to the lab
yesterday passed inspection and to hang them in plasic boxes. This to be
done before a King Air PBL mission today over the Central legs.
- arrive 0755
- installed plastic box and krypton electronics by climbing
- rewired CR10x power to stand-alone 3rd battery
- copied /card
- depart 0822
200: Site_visit, Site 8, Thu 06-Jun-2002 10:55:24 CDT, Site 8 visit
[This typed in 6 Jun for stuff done 5 Jun since I was too soggy yesterday.]
Peggy Lemone and Fei Chen visited yesterday. I took them to sites 7,9,8 while
I rehung krypton electronics (which were cleaned up and had new 6-pin connectors
installed in the trailer) in plastic boxes and downloaded /card. All of these
were serviced by climbing -- the towers were not dropped.
It was raining during all of these visits, so all kryptons were wet. All
krypton signals were only ~30mV -- hopefully they will recover.
I intended to do the logger power rewiring at s7 and s9, but forgot to bring
power cables :(
Approximate times were:
s7: 1340-1420 (drove in -- Peggy walked)
s9: 1530-1600 (started to drive in, got stuck in the mud!)
s8: 1630-1700 (walked in) had error downloading /card; DID NOT GRAB SDR
199: Site_visit, Site 9, Thu 06-Jun-2002 10:55:17 CDT, Site 9 visit
[This typed in 6 Jun for stuff done 5 Jun since I was too soggy yesterday.]
Peggy Lemone and Fei Chen visited yesterday. I took them to sites 7,9,8 while
I rehung krypton electronics (which were cleaned up and had new 6-pin connectors
installed in the trailer) in plastic boxes and downloaded /card. All of these
were serviced by climbing -- the towers were not dropped.
It was raining during all of these visits, so all kryptons were wet. All
krypton signals were only ~30mV -- hopefully they will recover.
I intended to do the logger power rewiring at s7 and s9, but forgot to bring
power cables :(
Approximate times were:
s7: 1340-1420 (drove in -- Peggy walked)
s9: 1530-1600 (started to drive in, got stuck in the mud!)
s8: 1630-1700 (walked in) had error downloading /card; DID NOT GRAB SDR
198: Site_visit, Site 7, Thu 06-Jun-2002 10:44:49 CDT, Site 7 visit
[This typed in 6 Jun for stuff done 5 Jun since I was too soggy yesterday.]
Peggy Lemone and Fei Chen visited yesterday. I took them to sites 7,9,8 while
I rehung krypton electronics (which were cleaned up and had new 6-pin connectors
installed in the trailer) in plastic boxes and downloaded /card. All of these
were serviced by climbing -- the towers were not dropped.
It was raining during all of these visits, so all kryptons were wet. All
krypton signals were only ~30mV -- hopefully they will recover.
I intended to do the logger power rewiring at s7 and s9, but forgot to bring
power cables :(
Approximate times were:
s7: 1340-1420 (drove in -- Peggy walked)
s9: 1530-1600 (started to drive in, got stuck in the mud!)
s8: 1630-1700 (walked in) had error downloading /card; DID NOT GRAB SDR
197: Site_visit, Site 6, Thu 06-Jun-2002 10:43:47 CDT, Site 6 visit
Kr electronic boxes collected from central sites.
Site 6, arrived 10:44, Kr 1397 box removed, cables bagged, departed 10:55
Note (7/26/02) This visit on June 5. See entry 204. TWH
196: Site_visit, Site 5, Thu 06-Jun-2002 10:43:34 CDT, Site 5 visit
Kr electronic boxes collected from central sites.
Site 5, arrived 9:10, mast dropped, Kr 1101 box and head removed, cables bagged
solar panel disconnected, departed 9:45
Note (7/26/02) This visit on June 5. See entry 204. TWH
195: Site_visit, Site 4, Wed 05-Jun-2002 14:26:32 CDT, Site 4 visit
Kr electronic boxes collected from central sites.
Site 4, arrived 8:48, Kr 1390 box removed, cables bagged, departed 8:55
Note (7/26/02) This visit on June 5. See entry 204. TWH
191: Site_visit, Site 7, Tue 04-Jun-2002 18:23:24 CDT, Site 7 visit
Arrived in heavy rain at 14:40.
Drove only to gate. Steve ran to station, climbed up and removed Kr electronics
Departed at 15:00
190: Site_visit, Site 9, Tue 04-Jun-2002 18:22:06 CDT, Site 9 visit
Arrived 13:15
Removed Kr 1394 and took to Base.
Departed at 13:25
189: Site_visit, Site 8, Tue 04-Jun-2002 18:15:43 CDT, Site 8 visit
Arrived 11:50
Dragged fresh N2 gas cylinder to cache and replaced existing cylinder at 12:00
From the west
8/4 1890 psi/ 8.5 psi
8/1 capped
8/3 2050 psi/ 8.5 psi
orig N2 320 psi/ 5 psi, new N2 2500 psi/ 5 psi
355.8 ppmv 1890 psi/ 9 psi
Ventilator fans all operating. Disconnected power at Campbell.
Swapped SDR #2 => #5
Downloaded /card
Dropped mast, removed Kr 1393 electronics and took to Base. Tested plastic box
Kr containment.
Mast up at 12:35, departed.
187: Site_visit, Site 5, Mon 03-Jun-2002 18:51:45 CDT, Site 5 visit
Arived 17:10
Installed Cu ground wire from Eve box to ground rod.
Reconnected Siamise ribbon cable connector; only power needed to be seated,
Tsurf was already OK
Dumped /card
Departed 17:33
185: Site_visit, Site 4, Mon 03-Jun-2002 18:43:46 CDT, Site 4 visit
Arrived at 16:12
Cleaned Kr
Again tested Kr 1392 after an attempt by Steve to clean off the corrosion.
No avail. The Kr 1392 will be Fed Ex'd to Steve Semmer this evening.
CR10X power from separate battery. Had to keep ground wire connected to keep
the logger operating.
Removed the H2O from the 9-pin amp
Reseated EVE AD connectors
Dumped /card
Departed 17:05
184: Site_visit, Site 9, Mon 03-Jun-2002 18:33:52 CDT, Site 9 visit
Arrived at 11:05
Dropped mast, cleaned Kr, checked Y cable and taped up all the ports on the mast
Checked/tightened rad stand multiplexer screws
For the three soil multiplexers, tightened screws and grounded common shields
Ventilator fan on downlooking K&Z not operating. Replaced with spare Nitec.
Then disconnected power to all ventilator fans.
Dropped mast for a second time and after trying the electronics and head of
1392, which had been taken from site 5 on 30 May, reinstalled the original Kr
1392 will be Fed Ex'd to Steve Semmer this evening
Tony checked the electric fence.
Departed at 12:58
180: Site_visit, Site 6, Sun 02-Jun-2002 14:16:33 CDT, site 6 visit
Arrived at 13:05, departed at 13:55
Eve cables shielded from RF in "standard" fashion.
Standard fashion is:
Ground strap over KH2O cable: front panel -> serializer
Aluminum foil and duct tape over EVEAD cable: front panel -> EVEAD
Soil multiplexer screws tightened, Shields gathered to common ground.third hole
Attempted to obtained clods but soil too sandy to gather as clods
179: Site_visit, Site 5, Sun 02-Jun-2002 13:52:06 CDT, Site 5 visit
arrived 11:15 departed 11:55
GOES DCP returned to location inside door
Standard RF shielding procedure implimented
Soil multiplexer shields gathered for common ground with the cables associated
with the multiplexer output
Data captured as s5.02.06.02
.2 points added by SO
1. I think I forgot to connect a copper ground wire to replace the ground
strap that I removed. We should do this before the next electrical storm.
2. I seem to recall seeing that the battery voltage was low. This might be
a mis-seated AD0 connector on the EVEAD (they are hard to align!) I should
have checked this as well.
178: Site_visit, Site 4, Sun 02-Jun-2002 13:51:40 CDT, Site 4 visit
Arrived 9:50
Downloaded card
Replaced braided ground strap with Cu wire
Kr cleaned
All screwstightened in soil multiplexer and shields gathered to common ground
All screws tightened in radstand multiplexer
Returned GOES box to position inside door and signal cables shielded against RF
Departed 11:05
Returned at 12:05 to check the placement of the soil multiplexer shield ground.
It had been in second from left ground. It was replaced in the first ground.
176: Site_visit, Site none, Sat 01-Jun-2002 21:43:04 CDT, Site 10 visit
Arrived at site 10 1/2mile west and 2 miles north of site #3, at 18:40
Obtained some dubious clods.
Leveled the radiometer
Departed at 19:10
175: Site_visit, Site 3, Sat 01-Jun-2002 21:38:32 CDT, Site 3 visit
Arrived 17:45
Cleaned Kr at 17:52
Tightened all screws of radstand Campbell multiplexer
Tightened all screws of soil multiplexer and grounded separated shields
Soil too sandy to obtain a clod
Dumped /card captured to S3.02.06.02
Shielded signal cables, Kr and A/D
Departed at 18:30
174: Site_visit, Site 2, Sat 01-Jun-2002 21:28:44 CDT, Site 2 visit
Arrived 15:16
Cleaned Kr and also removed spider web strings from sonic transducers.
Tightened all radstand Campbell screws
Wet cleaned the PSP and the Pyrg dome. They looked OK but the Pyrg pile
reading had been +ve previously and only returned to reasonable at the last
cleaning
Took "clods" for bulk density. 5mm crust with damp soil below. May not be
able to do clod method.
Steve tightened screws in soilmultiplexer and separated and grounded shields
Look at GOES jump, Tsurf 250, Kr = 0 before shielding
Shieled Kr and A/D cables .After shielding Tsurf and Kr GOES jumps small.
Dumped /card, captured to S2.02.06.02
Departed 16:10
173: Site_visit, Site 1, Sat 01-Jun-2002 21:08:39 CDT, Site 1 visit
Arrived 13:14 after driving from Wichita
Clean Kr at 13:21
The down-looking SW had been giving problems but showed no obvious reasons.
!3:35 - 13:45 removed K&Z 970380 and installed K&Z 940181. Did not change
Campbell coefficients
14:00 - 14:10 tightened all screws of radstand Campbell barrier strips
!3:50 took two "clods" of soil. Not very cohesive with 1 -2 cm crust and damp
uncosolidated soil underneath containing lots of crop residue.
Steve tightened all screws in soil multiplexer and separated the soil profile
shields and grounded them separately to the signal grounds
Steve shielded the EVE power and serializer cables. Before shielding
Kr = 250mv and Tsurf = 0 and afterwards was small.
Captured s1.02 06:01
Downloaded /card and replaced SDR #6 with SDR #3 and left SDR #4 in the bag.
Bag now has SDR#1 and SDR#4
Departed 14:50
Departed at 14:50
170: Site_visit, Site 4, Fri 31-May-2002 13:50:36 CDT, Site 4 visit
We got to s4 about 1216. I captured a lot of stuff onto file s4.020531.
During this time, we captured a GOES transmission with Tsfc, I think, then
turned the station off from about 1222-1229 while I put braid (ground strap)
around the krypton signal cable in the EVE box. Upon restarting, the serializer
didn't come up, but did after I disconnected and reconnected the DB9 on it.
I then captured the KH2O during a transmission -- a jump was not apparent,
but the krypton signal was highly variable.
Turned GOES off at 1238.
Saw the King-Air go by E-W about 1/2mi north about 1300, turn around, and come
back a few minutes later. Took several boring photos of it -- Tony thinks he
got a good one with our tower in the foreground.
Took a dirt clod sample at 1320 and left the site.
168: Site_visit, Site 6, Fri 31-May-2002 11:33:35 CDT, GOES off at s6
We just finished a site visit to s6. (I'm writing this on aster on the road
to s4!) Since the King-Air is flying today 12:30-16:00 over the Central legs,
we decided to turn off all GOES transmitters from 4-6. (s5's we apparently
forgot to turn on at the end of yesterday, so it is already off.)
Our sequence was:
- 10:46 turned off GOES (SE120)
- a few minutes later decided to turn back on and log "jump"
- captured end of Tsfc jump -- not very apparent -- as "s6" (will rename later)
- had to reboot EVE and restart minicom since console locked up
- captured KH2O jump (not obvious, but large fluctuations) and next Tsfc jump
(160 counts = 16mV) as "s6.2"
- copied /card to Panasonic
- decided that krypton voltage was low (~150mV), so we cleaned by quickly
dropping the mast, cleaning ~11:00, and reraising. New value is ~320mV.
(We want good krypton data for today's flight.)
- 11:06 unplugged GOES again and headed off to s4.
Noted that TRH fan was okay and prop was spinning.
166: Site_visit, Site 4, Thu 30-May-2002 19:16:39 CDT, Site 4 visit
Arrived at 16:00.
There were oil-field workers doing things near the site.
The mast was not lowered.
The Kr was cleaned and signal improved from 150 mv to 460 mv
The TRH fan sounded OK as did the radstand multiplexer.
Following the procedure adapted at site 5 we removed the GOES DCP transmitter
and repositioned it outside and below the EVE box, with a tupperware cover.
Then we discovered that there still was GOES interference of 180 counts on Tsfc.
(Unfortunately we had not tested for noise before making the change)
We also captured the data from /card.
165: Site_visit, Site 5, Thu 30-May-2002 18:59:16 CDT, Site 5 visit
Arrived at site 5 at ~ 13:30 and began a series of test on the GOES interference
At 13:50 began data capture, at 13:58:20 stopped data capture. This to record
the Tsfc and KH2O steps during a GOES transmission. This file saved to
captures/s5.020530.
At 14:05 dropped mast and cleaned the Kr windows.
The signal increased (only) from 900 to 940 mV. This like a good
level, but the dailyplots show bad data. Hopefully, it is just a connector
problem (though Gordon and Tom had looked at this before.)
At 14:15 demounted the Kr #1392 and replaced it with Kr # 1101. This Kr sensor
had been brought into the base and had had the obvious corrosion inside the
electronics box removed and fresh silica gel in a cloth bag included. The
electronics box was also better sealed.
The signal changed Kr #1392 900mv to Kr # 1101 300 mv ( a decrease but hopefully
a more stable sensor).
The TRH fan sounded fine, the Rad stand multiplexer sounded fine and the
propvane spun with no noise. The ports in the mast had already been duct taped and so it was assumed that the Y cable had been inspected.
The GOES tests result:
noise even when Yagi deployed 10 m away
noise even with a dummy load
reduction of noise on Tsfc from 250 counts to 15 counts when GOES transmitter
box outside the Eve box
As a result we rigged the cables out through a hole in the bottom of the box
and placed the GOES box atop a battery box with a tupper ware cover.
We also captured the data from /card.
P.S. GOES data have stopped from this site. We may have left the switch on the
transmitter off. We'll have to run out again -- I don't think now, since it
is late and Tony has left. We'll plan on a run tomorrow -- they're planning on
flying this area anyway!
162: Site_visit, Site 8, Wed 29-May-2002 23:28:05 CDT, Site 8 visit
We also hit s8 today, after s7 (approx 1600-1840) and did lots of things:
- We discovered the ventilator fan on LW.out was dead. Checked it was fan and
not the power by swapping power with LW.in.
- We checked the gas cylinder pressures of Scott's CO2 system
In order from the west (could not view all writing on cylinders):
Site 8/4, 415.1 ppmv 2000 psi/8 psi
Site 8/1, capped
Site 8/3 2150 psi/8 psi
Nitrogen 850 psi/4.5 psi
Site 8/2, 355.8 ppmv 2000 psi/8 psi
- We lowered the mast about 1700-1830. During this time, we:
- cleaned the krypton
- noted that the prop was stuck with dirty bearings. We unscrewed the
prop end and sprayed with contact cleaner which got the shaft running
much better, though there still is a grinding noise
- examined the Y junction in the S-bus cable and decided it was okay.
We taped most of the holes with duct tape anyway.
- We disconnected power to the GOES transmitter and left it off. (After
verifying that the A/D problem still was present, though only about 70
counts here.)
- We tightened all the CR10x screws -- some were loose.
- We tightened all the screws in the soil profile box -- many weren't tight.
(after labeling the Echo probe wires, so we could put it back together)
- We disconnected 229 heating for a while to see if heating is causing the
noise. This was a bad test, I think, since the 229 output went offscale
and became 9999. (I don't understand why!)
- We connected all the 229 shields directly to power supply ground.
- We downloaded /card (twice!) (to examine the 229 data)
- We swapped the microdrive disk (replaced 2 with 5)
Tony found a tick crawling on the Eve box. Steve killed it.
Upon returning to the base, we did a "save_metppf" to get the data to Boulder.
This script died during the rsync to linus, so I repeated the last 2 steps
manually from ASTER.
P.S. The data seem to show no effect of the shield wire change or the screw
tightening efforts.
For next visit we need to take a radiometer ventilator fan and a propvane
161: Site_visit, Site 7, Wed 29-May-2002 23:19:08 CDT, Site 7 visit
We did several things at site 7. Our primary reason for the visit was to see
if the glitch in the analog channels seen in the high-rate data at s8 also
occurred at non-supersites. Using "sbusdebug" to watch Tsfc voltages, it was
obvious that the glitch does occur here. The counts = 0.1mV changed by ~250
when the GOES transmitter was on. I captured a bit of this on the Panasonic
using minicom (this file is now in $PAM/projects/IHOP02/captures/s7.020529).
We further found out
by attaching the dummy RF load that this problem disappears. Thus, it is an
RF interference problem. We moved the antenna from the SW to E leg of the
tripod, but this didn't appear to work. (Note that we left it in this position
which is rather close to the sonic.) During the process, I rebooted a few
times and even powered-off the station once. Note that the /card data should
recover much of the data while the GOES was off.
We left the station with GOES back running and the antenna near the sonic.
During all of this, an EVE error started appearing: "Illegal Address, 21 ticks".
Since all of the data channels appeared to be working, we ignored this.
Also, it seemed to me that the CR10x data didn't get started after one of the
reboots, so I used "lineon 2"; "lineoff 2" to get it going again. I'm assuming
that this really wasn't necessary.
156: Site_visit, Site 7, Tue 28-May-2002 16:45:43 CDT, Site 7 visit
Visited site 7, 1220-1505 CDT, May 28
Replaced TRH206 w/ TRH003. TRH206 blew the Sbus fuse. It is a 2 amp
fuse, but none was available, so I replaced it with a 3 amp fuse.
Downloaded local storage.
Opened KH2O electronics and was corroded again. Cleaned internal
power connector terminals and applied Seal & Peel to internal
connectors. Cleaned KH2O windows.
Tightened terminal screws in Campbell data logger enclosure.
154: Site_visit, Site 6, Tue 28-May-2002 10:19:38 CDT, Site 6 visit
Visited site 6, 1653-1723 CDT, May 27
Lowered mast, 1700-1715 CDT
Cleaned radiometers
Cleaned KH2O
Opened KH2O electronics and looks okay. Applied Seal & Peel to internal
connectors of KH2O
152: Site_visit, Site 4, Tue 28-May-2002 10:14:34 CDT, Site 4 visit
Visited site 4, 1305-1330 CDT and again 1553-1605 CDT, May 27
First visit:
Cleaned radiometers
Cleaned KH2O
Tightened terminal screws in logger box, but not profile multiplexer box
Downloaded local data storage
Took 360 degree photos.
Measured heater voltage for 229 soil sensors at 1.6 VDC
Second visit:
Opened KH2O electronics and looks okay. Applied Seal & Peel to internal
connectors of KH2O
149: Site_visit, Site 5, Tue 28-May-2002 10:03:50 CDT, Site 5 visit
Visited site 5, 1130-1255 CDT and again 1447-1542 CDT, May 27
First visit:
Mast lowered 1147-1217 CDT.
Installed KH2O 1101, cleaned
Cleaned radiometers, everest
Tightened terminal screws in logger box, but not profile multiplexer box
Downloaded local data storage
Took 360 degree photos.
Found KH2O 1392 power terminals corroded again! Recleaned and
applied Seal and Peel directly to the internal terminals of the
connector.
Second visit:
Mast lowered 1505-1530 CDT.
Replaced KH2O 1101 w/ 1392 after refurbished. Cleaned windows.
143: Site_visit, Site 6, Sun 26-May-2002 17:32:54 CDT, Site 6 visit
Visited station 6 from roughly 1445 - 1645 CDT, May 26
Restarted prop vane to cure direction error
Downloaded slow data
Tightened terminal screws in Campbell data logger and multiplexers
Changed sonic samples from 10 to 11 pulses per data output
Took 360 degree photos
Gordon downloaded Campbell logger program.
139: Site_visit, Site 9, Sun 26-May-2002 10:42:11 CDT, Site 9 visit
Site visit, May 25, roughly 1630 - 2030 CDT
Downloaded slow data.
Recorded soil profile data on independent data loggers for profiles
9 and 13.
Noted that Rsw, Rlw, Rnet, Tsoil, Gsoil data all missing. Removed logger
enclosure from radiation sawhorse to replace multiplexer. Started to
replace multiplexer and found some loose terminal screws, in particular
the L1 common terminal between the 6 and 7 groups of terminals.
Tightened them and replaced logger on sawhorse.
Gordon also repaired an exposed, broken wire on soil profile 9.
137: Site_visit, Site 4, Sat 25-May-2002 12:21:37 CDT, Site 4 visit, May 22
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
18) Site 4: 5/22/02
Arrival: 1551
Departure: 1755
Conditions: overcast, though decent light penetration, strong SSW winds
Observers: JA & JU
-Radiometers cleaned
-Surface Characterization transects selected:
(i) western transect begins 20m west of radiometer 'saw horse', extends
for 20m and is marked with orange flags every 5m
(ii) southern transect begins 20m south of radiometer 'saw horse',
extending for 20m with orange flags every 5m
-Surface Characterization:
(i) Gravimetric soil core sample collected 10m west of radiometer
'saw horse' at 1606
(iii) Trime measurements next to soil moisture profiler and soil core,
as well as along western and southern transects.
(iv) IR surface temperature distribution with vegetation height taken in
field of view of flux tower IR instrument, 4 samples taken at 5 different
times. IR surface temperature distribution with vegetation height also
taken along western and southern transects
(v) MSR readings taken along western and southern transects as well as
in field of view of flux tower IR instrument.
(vi) LAI measurements taken in field of view of flux tower IR instrument
as well as along western and southern transects
(vii) Porometry data collected along transect
(viii) NO xylem potential measured since grass vegetation not compatible
with this procedure
(ix) Photographs taken of 4 cardinal directions and of dominant surface
types and vegetation.
(x) Digital photos taken of 4 cardinal directions and along western and
southern transect.
136: Site_visit, Site 5, Sat 25-May-2002 12:20:05 CDT, Site 5 visit, May 22
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
17) Site 5: 5/22/02
Arrival: 1213
Departure: 1525
Conditions: overcast, though with decent light penetration, strong SSW winds
Observers: JU & JA
- Radiometers cleaned and level checked at 1404
- Surface Characterization transect selected:
-Single NW transect selected along access road to flux tower, beginning
approximately 20m NW of solar panel array, extends 45m marked with orange
flags every 5m
- Surface Characterization:
(i) Gravimetric soil core sample collected 5m west of the solar panels
at 1252.
(iii) Trime measurements next to soil moisture profiler and soil core,
as well as along western and southern transects.
(iv) IR surface temperature distribution with vegetation height taken in
field of view of flux tower IR instrument, 4 samples taken at 5 different
times. IR surface temperature distribution with vegetation height also
taken along western and southern transects
(v) MSR readings taken along western transect as well as in field of
view of flux tower IR instrument.
(vi) LAI measurements taken in field of view of flux tower IR instrument
as well as along western transects
(vii) Porometry data collected along western transect.
(viii) NO xylem potential measured since winter wheat vegetation not
compatable with this procedure
(ix) Photographs taken of 4 cardinal directions and along western and
southern transect.
(x) Digital photos taken of 4 cardinal directions and along western and
southern transect.
135: Site_visit, Site 3, Sat 25-May-2002 12:19:03 CDT, Site 3 visit, May 21
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
16) Site 3: 5/21/02
Arrival: 1200
Departure: 1628
Conditions: Sunny, light SSW wind increasing to strong SSW wind as
day progressed
Observers: JA & JU
-Radiometers cleaned @ 1623
- Surface Characterization:
(i) Gravimetric soil core sample collected due west of the radiometer
sawhorses at the perimeter of the fence at 1620.
(iii) Trime measurements next to soil moisture profiler and soil core,
as well as along western and southern transects.
(iv) IR surface temperature distribution with vegetation height taken in
field of view of flux tower IR instrument, 4 samples taken at 2 different
times. IR surface temperature distribution with vegetation height also
taken along western and southern transects
(v) MSR readings taken along western and southern transects as well as
in field of view of Site 2 PAM flux tower IR instrument.
(vi) Porometry data collected along the western and southern
transects. Both of the dominant species, sage and "thorny bush", are
sampled. Note, final values can not be calculated until the actual LAI
is measure in the lab.
(vii) Photographs taken of 4 cardinal directions and along western and
southern transect and of the dominant plants.
(viii) Digital photos taken of 4 cardinal directions and along western
and southern transect.
134: Site_visit, Site 3, Sat 25-May-2002 12:17:30 CDT, Site 3 visit, May 20
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
15) Site 3: 5/20/02
Arrival: 1952
Departure: 2030
Conditions: partly cloudy, moderate south winds
Observers: JU & JA
-LAI taken in Site 3 PAM flux tower IR instrument field of view as well
as along western and southern transects
133: Site_visit, Site 2, Sat 25-May-2002 12:16:51 CDT, Site 2 visit, May 20
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
14) Site 2: 5/20/02
Arrival: 1409
Departure: 1901
Conditions: sunny, scattered cumulus to NW, strong SSW winds
Observers: JA & JU
-Radiometers cleaned and level checked at 1620 (?).
-Surface Characterization transects selected:
(i) western transect begins 25m west of Site 2 radiometer 'saw horse',
extends for 20m and is marked by orange flags every 5m
(ii) southern transect begins 20m south of radiometer 'saw horse',
extends for 20m and is marked with orange flags every 5m
-Surface Characterization:
(i) Gravimetric soil core sample collected 10m west of the radiometer
"sawhorses" at 1447.
(iii) Trime measurements taken next to soil moisture profiler and soil
core, as well as along western and southern transects.
(iv) IR surface temperature distribution with vegetation height taken in
field of view of flux tower IR instrument, 4 samples taken at 2 different
times. IR surface temperature distribution with vegetation height also
taken along western and southern transects
(v) MSR readings taken along western and southern transects as well as
in field of view of flux tower IR instrument.
(vi) LAI measurements taken in field of view of flux tower IR instrument
as well as along western and southern transects
(vii) Porometry data lost due to improper baud rate during download -
information garbled and deleted from storage device
(viii) NO xylem potential measured since dominant 'vine-weed' vegetation
not compatible with this procedure
(ix) Photographs taken of 4 cardinal directions and of the "vineweed".
(x) Digital photos taken of 4 cardinal directions and along western and
southern transect.
132: Site_visit, Site 1, Sat 25-May-2002 12:14:32 CDT, Site 1 visit, May 20
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
13) Site 1: 5/20/02
Arrival:1019
Departure: 1335
Conditions: clear, few high cirrus clouds, wind strong from SSW
Observers: JU & JA
-Site 1 radiometers cleaned @ 1219, no damage or significant debris
(only light dust)
-storage media flash card recording lights checked, top light: off, 2nd
from top light: flashing, bottom 2 lights solid - equipment recording
properly.
-Surface Characterization transects selected
(i) western transect begins 20m west of radiometer 'saw horse' and
extends for 20m, marked by orange flags every 5m
(ii) southern transect begins 20m south of radiometer 'saw horse' and
extends for 20m, marked by orange flags every 5m
-Surface Characterization:
(i) Gravimetric soil core sample collected 5m west of the solar panels
at 1100.
(ii) Trime samples taken next to 3 soil moisture profiler locations and
soil core sample location as well as along western and southern transects
(iii) IR surface temperature taken in field of view of Site 1 PAM
IR temperature instrument: 4 samples taken at 2 different times - no
vegetation present to measure such IR temp distribution with height. IR
surface temperature also taken along western and southern transects.
(iv) MSR measurements taken in field of view for flux tower IR temperature
sensor as well as along western and southern transects
(v) NO LAI taken due to absence of vegetation
(vi) NO porometry measurements due to absence of vegetation
(vii) NO xylem potential measurements taken due to lack of vegetation
(viii) Photographs taken of 4 cardinal direction . Digital photographs
taken of 4 cardinal directions as well as along western and southern
transects
131: Site_visit, Site 3, Sat 25-May-2002 12:13:20 CDT, Site 3 visit, May 18
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
10) Site 3: 5/18/02
Arrival: 1221
Departure: 1840
Conditions: clear with few cirrus clouds to the NW, SSE winds light to
moderate Observers: JA & JU
-Began disassembly of CU flux station after data download. Due to a
"hiccup" with the software the data was downloaded via laptop. This
appears to have reset the program as follow-up test downloads to the
SM4 storage module have proceeded as normal.
-Digital pictures of Site 3 four cardinal directions taken at ~1453
-Surface characterization transects selected:
(i) western transect beginning located 20m north and 20m west of solar
panel array (NW corner of fencer), extends for 20m and is marked by
orange flags every 5m
(ii) southern transect beginning located 20m south of flux tower cow
fencer directly south of net radiometer, extends 20m and is marked with
orange flags every 5m
130: Site_visit, Site 6, Sat 25-May-2002 12:12:12 CDT, Site 6 visit, May 17
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
9) Site 6: 5/17/02
Arrival: 1530
Departure: 2015
Conditions: sunny, very few isolated clouds, light to moderate wind NNE
-Radiometers cleaned at 1721; domes appeared free of debris - net
radiometer level.
-Single surface characterization transect selected beginning about 40m
north of Site 6 flux station solar panel array, extending for 45m with
every 5m marked with orange flags denoting sampling point (including
endpoints)
-Gravimetric soil core taken at 1736 about 5 m west of solar panel array
-IR surface temperature distribution with vegetation height taken in
field of view of Site 6 flux station IR temperature sensor (about 3m
north of flux station tripod); 4 samples taken at 2 different times
-IR surface temperature distribution with vegetation height taken along
surface characterization transect of Site 6
-Digital photos of 4cardinal directions taken at 1917
-Photographs of the 4 cardinal directions taken.
-LAI and MSR measurements taken of sampling transect as well as in field
of view of PAM flux tower IR view.
129: Site_visit, Site 7, Sat 25-May-2002 12:09:54 CDT, Site 7 visit, May 16
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
8) Site 7: 5/16/02
Arrival: 1550
Departure: 1705
Conditions: heavy overcast, light NE winds, light 'sprinkle of rain for
about ten minutes at 1705
-Radiometers cleaned at 1700, some dust on domes prior to cleaning
-Gravimetric soil core taken at 1654
-Cuttings of the representative species to be used for porometry were
taken for identification purposes.
128: Site_visit, Site 8, Sat 25-May-2002 12:09:10 CDT, Site 8 visit, May 16
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
7) Site 8: 5/16/02
Arrival: 14:05
Departure: 1600
Conditions: heavy overcast, very light SE breeze, moderate rain fell
for about ten minutes around 1535
-IR surface temperature distribution with vegetation height taken in
field of view of Site 8 flux station IR temperature sensor just outside
of cow fencer (about 3m north of fencer)
-Site 8 radiometers cleaned at 1449, some debris accumulated prior
to cleaning. ***Top dome of net radiometer had small crack on lower
edge at '2 o'clock' orientation for observer facing north***
-Swapped storage card #5 for storage card #1 (also marked 04/02) and
delivered to ISSF trailer
-Gravimetric soil core taken at 1530
-2 land surface characterization transects selected
(i) Western transect begins approximately 30m west of radiometer
instrumentation and extends for 20m - beginning and end of transect
marked with blue flags
(ii) Southern transect begins approximately 20m south of radiometer
instrumentation and extends for 20m - beginning and end of transect
marked with blue flags
- Photographs in the cardinal directions, selected vegetation, and
transects taken.
- Trime measurements taken next to the soil profiler and where the core
sample was collected.
127: Site_visit, Site 9, Sat 25-May-2002 12:07:39 CDT, Site 9 visit, May 16
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
6) Site 9: 5/16/02
Arrival: 1017
Departure: 1400
Conditions: heavy overcast, moderate SE winds
-Radiometers cleaned at 1318, relatively free of debris prior to cleaning
though some dust present
- One of the thin black wires leading to Profiler 9 found to have a cut
in the sheathing. The wire was repaired and flagged with electrical
tape. Additionally, one of the heavy black wires leading to profiler
9 was found to be severed and could not be repaired. - One of the
thin black wires leading to Profiler 8 was found to have a cut in the
sheathing. The wire was repaired and flagged with electrical tape.
-Surface characterization measurements taken:
(i) IR surface temperature distribution with vegetation height in field
of view of Site 9 flux station IR temperature instrument
(ii) IR surface temperature distribution with vegetation height in field
of view of Site 9 flux station IR temperature instrument; 4 samples
taken at two different times
(iii) Gravimetric soil core taken at 1122 approximately 5m west of
radiometer instrumentation just outside perimeter of 'cow fencer' next to
the fourth 'cow fencer' post from the right of the fencer entrance gate.
(iv) IR surface temperature distribution with vegetation height taken
on western transect every 5m for 20m including endpoints
(v) IR surface temperature distribution with vegetation height taken on
southern transect every 5m for 20m including endpoints
(vi) Leaf area index measured along the western transect every 5m for
20m including end points.
(vii) Leaf area index measure along the southern transect every 5m for
200m including the endpoints.
(viii) Trime measurements taken next to each of the soil profilers and
the site where the soil core was taken.
(ix) Trime measurements taken along the western transect every 5m for
20m including endpoints.
(x) Trime measurements taken along the southern transect every 5m for20m
including the endpoints.
(xi) Photographs of the site taken in each of the cardinal directions;
additional images of selected vegetation taken.
(xii) MSR could not be collected due to heavy overcast weather conditions.
(xiii) Representative plants for porometry chosen within the fencer;
vegetation along the transects is subject to grazing.
(xiv) Xylem potential attempted on two of same species as the porometry
will be collected. However, due to either the free flowing nature of the
sap and/or the architecture of the plant, data collection is not feasible.
126: Site_visit, Site 7, Sat 25-May-2002 12:06:41 CDT, Site 7 visit, May 15
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
5) Site 7: 5/15/02
Arrival: mid-afternoon
Departure: mid-afternoon
-No maintenance or measurements performed, only visited site for survey
with David Yates to discuss surface characterization and sampling method
125: Site_visit, Site 6, Sat 25-May-2002 12:05:56 CDT, Site 6 visit, May 14
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
4) Site 6: 5/15/02
Arrival: 1200
Departure: early afternoon
-No maintenance or measurements performed, only visited site for survey
with David Yates to discuss surface characterization sampling method
124: Site_visit, Site 9, Sat 25-May-2002 12:04:50 CDT, Site 9 visit, May 14
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
3) Site 9: 5/14/02
Arrival: 1535
Departure: 1930
Conditions: mostly sunny, light wind
-2 land surface characterization transects selected
(i) Western transect begins approximately 20m west of PAM radiometer
instrumentation and extends for 20m - beginning and end of transect
marked with blue flags (ii) Southern transect begins approximately 20m
south of PAM radiometer instrumentation and extends for 20m - beginning
is marked with a blue flag and end is marked with a green flag
-Assistance provided to Tom Horst to lower flux station mast for service
123: Site_visit, Site 3, Sat 25-May-2002 12:03:48 CDT, Site 3 visit, May 11
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
2) Site 3: 5/11/02
Arrival: 1000
Departure: 1140
Conditions: partly cloudy, windy
-Soil heat flux sensor 1 connection loose, therefore no data logged for
that parameter for the preceding 24 hours. Cause: loose wire, corrected
by Joe Alfieri
-Soil temperature probe 10 Ohm resistor installed, probe still not
functional. Cause: 100 Ohm resistor required instead of 10 Ohm resistor
-> to be installed on 5/18/02 when CU flux station is moved to Site 10.
-CU flux tower net radiometer leveled, pyrometer leveled, and surface
IR temperature sensor knob adjusted 100% clockwise for proper adjustment
of emissivity of 1.
-Photographs taken of both Site 3 PAM flux station and CU flux station
as well as Site 3 landscape in 4 cardinal directions.
122: Site_visit, Site 3, Sat 25-May-2002 11:57:10 CDT, Site 3 visit, May 10
TWH extracted the following from Josh Uebelherr and Joseph Alfieri
email recieved 5/25/02
1) Site 3: 5/10/02
Arrival: 1015
Departure: 1600
Conditions: heavy overcast, very windy
-Site 3 PAM station radiometers cleaned with 'kim wipes' at 1315 - domes
intact, net radiometer level, and all domes relatively free from debris
though some dust was on surface.
-CU flux station (for site 10) placed at site 3 for cross calibration
approximately 35 m WSW (221 degrees) of the site 3 PAM station (elevation
of CU station placement approximately 1m lower elevation than site 3
PAM station).
-The sonic anemometer and krypton hygrometer on the CU flux station
oriented to face true north per the instruction of Dr. Blanken. However,
since the dominant winds in the region are from the south, when the
tower is relocated to Site 10 these instruments will be oriented facing
east. The pyrometer and net radiometer are facing south and the IR
thermometer is monitoring surface temperature to the southeast of
the tower.
- The soil measurements associated with the CU flux station are taken
such that the CS615 probes collect soil moisture content at 5, 7.5, and
15cm; the pair of soil heat flux plates are placed on either side of the
CS615s at a distance of 10cm from center and at a depth of 5cm; the soil
temperature probe (not functional) is placed directly above the column
of CS615 at a depth 2.5cm. The entire collection of sensors is located to
the south west of the tower just outside the view of the net radiometer.
-CU flux station soil temperature sensor not functional due to missing
resistor.
115: Site_visit, Site 1, Wed 22-May-2002 19:28:58 CDT, Site 1 visit
Site visit, May 22, 16:40 CDT
Replaced EVE EPROM (won't print console mesage on non-zero CSAT diags)
old: EVE 4/21/02 6047
new IHOP02 5/14/02 0xA7BA
Downloaded slow data.
Removed microdrive #2
Inserted #3.
Left #1 and #6 inside EVE box.
Krypton had slight oxidation, see entry 116
Voltage at soil profile multiplexer and campbell logger: 11.2V
Installed new power supply & battery, see entry #117, which brought
voltage up to 13.2V at Campbell boxes, and 13.8V at EVE.
Nitrogen: 425 PSI (Scott called and will try to have that cylinder
replaced this weekend).
Left around 18:30
113: Site_visit, Site 2, Wed 22-May-2002 19:17:47 CDT, Site 2 visit
Site visit, May 22, 15:40 CDT
Replaced EVE EPROM (won't print console message on non-zero CSAT diags)
old: EVE 4/19/02 4FC6
new IHOP02 5/14/02 0xA7BA
Downloaded slow data.
Krypton was in good shape, see entry 114
Voltage at soil profile multiplexer and campbell logger: 13.8V
Left 16:04. P3 flew over several times at ~1000ft
111: Site_visit, Site 3, Wed 22-May-2002 19:00:34 CDT, Site 3 visit
May 22 14:00CDT
Installed new EVE eprom (won't print console message on non-zero CSAT diags)
old: EVE 4/21/02 6047
new: IHOP02 5/14/02 0xA7BA
Note: this station does not have anything connected to the PULSE
port on the VME front panel. Is that right? The Profile
variable is cycling through its values 0-2. The logger must be
doing it itself?
On power up, the 5A main fuse on the front panel blew. Relaced it
and next power-up was successful.
Downloaded slow data
Voltage at soil profile multiplexer and logger: 13.6 V
Tom opened up and cleaned krypton box: see entry 112.
Left at 14:40 CDT
109: Site_visit, Site 7, Tue 21-May-2002 16:39:17 CDT, Site 7 visit
Tom visted site 8 1455 - 1515 CDT, May 21
Took site photographs. First took two pictures of site from SE, then
two consecutive series of photos from next to the tripod at 45 degree
azimuth intervals, starting from North and proceeding clockwise
through E,S,W,N.
108: Site_visit, Site 8, Tue 21-May-2002 16:38:06 CDT, Site 8 visit
Tom visted site 8 1400 - 1455 CDT, May 21
Took site photographs. First took two pictures of site from SE, then
two consecutive series of photos from next to the tripod at 45 degree
azimuth intervals, starting from North and proceeding clockwise
through E,S,W,N.
107: Site_visit, Site 9, Tue 21-May-2002 16:32:21 CDT, Site 9 visit
Tom visted site 9 1200 - 1320 CDT, May 21
Reset the GOES clock wrt GPS and downloaded the local data storage.
Tried new 16 MB PCMCIA flash disk by rebooting EVE from stored
configuration. This appeared to worked okay.
Measured Campbell multiplexer and logger supply voltages as 12.7 V.
Took site photographs. First took two pictures of site from SE, then
two consecutive series of photos from next to the tripod at 45 degree
azimuth intervals, starting from North and proceeding clockwise
through E,S,W,N.
105: Site_visit, Site all, Mon 20-May-2002 11:17:02 CDT, Site visit check list
Clean optical sensors
---------------------
Clean PSP, PYG, Rnet, Rpar radiometers on dark horse
Check Rnet bubble level
If mast is lowered:
Note times when mast is lowered and raised
Clean kh2o
Clean Everest
Shoot prop and sonic azimuths with KVH data scope
Declinations are west 7.5 deg, central 6 deg, east 5 deg
Else
Clean kh2o if within reach
EVE
---
Check and reset GOES clock with GPS
At sites 1 and 8 swap SDR microdrive (1 wk capacity)
Download (slow) local data storage; reboot EVE
KH2O
----
Clean internal power connector leads on stns 1:3,8
Soil profiles
-------------
Measure multiplexer and logger supply voltages at site 1:5,9
Test electric fence as applicable
If Joe and Josh are not taking soil moisture measurements,
then take a Trime reading near the ATD Qsoil and take a Trime
reading and soil sample outside the radiometer footprints.
101: Site_visit, Site 8, Mon 20-May-2002 09:16:05 CDT, Site 8 visit
Tom visted site 8 5:15 - 7:05 pm CDT, May 19.
Replaced net radiometer, set GOES clock, downloaded (slow) local
data storage.
Measured multiplexer and CR10 supply voltages: 11.6 V
99: Site_visit, Site 7, Mon 20-May-2002 09:10:23 CDT, Site 7 visit
Tom visted site 7 2:45 - 4:45 pm CDT, May 19.
Cleaned the kh2o head and the power connector inside the electonics
box, reset the GOES clock, and downloaded the local data storage.
Replaced EVE prom EVE 4/21/02 6047 with IHOP02 5/14 0xA7BA
Measured multiplexer and CR10 supply voltages: 14.0 V
95: Site_visit, Site 6, Sat 18-May-2002 15:07:54 CDT, Site 6 visit
Gordon and Tom visted site 6 13:50 - 19:10 CDT, May 18, including two
trips back to Wichita base.
We cleaned the kh2o head and the power connector inside the electonics
box, checked the clock, and downloaded the local data storage.
We returned to the base, leaving the mast down, in order to repair
a broken connector inside the kh2o electronics and again to get a
cable needed to zero the NUW sonic.
See entry #97 about the attempted zeroing of the NUW#5 sonic, and
the eventual replacement with a K probe #980202.
Measured the power voltage at the campbell logger and multiplexer: 12.8 V.
The mast was down from 13:55 - 19:00 CDT.
Talked with Ken Andra at site.
93: Site_visit, Site 5, Sat 18-May-2002 14:59:35 CDT, Site 5 visit
Gordon and Tom visted site 5 11:00 - 12:00 CDT, May 18.
We cleaned the kh2o head and the power connector inside the electonics
box, reset the clock (from 2 sec fast to 1 sec slow), and downloaded
the local data storage.
Gordon sealed the Y in the Sbus cable with splicing tape and Peel
and Seal. He also filed the inside of the TRH boom and remounted
the TRH inside the boom.
The mast was down from 11:10 - 11:50 CDT.
90: Site_visit, Site 4, Sat 18-May-2002 14:49:55 CDT, Site 4 visit
Gordon and Tom visted site 4 9:46 - 10:42 CDT, May 18.
We installed a new prom in EVE, cleaned the kh2o head and the
power connector inside the electonics box, and downloaded the
local data storage.
79: Site_visit, Site 8, Thu 16-May-2002 10:58:05 CDT, Site 8 visit
Visited site 8 on May 16, to fix barometer, get fast & slow data,
and check GOES.
See entries 80,81,82
74: Site_visit, Site 5, Thu 16-May-2002 09:56:13 CDT, Site 5 visit, May 12
Arrived 17:30, CDT
Prop vane reporting constant wind direction, -99
Prop PO command reported jibberish.
TRH out.
Replaced TRH 104 with 704. 704 reported data.
Removing TRH was difficult, needs crossarm expansion fix
TRH704 is lashed under cross arm rather than inserted in end
TRH cable was dripping water. Water in TRH connector.
Removed end cap of TRH housing, electronics were dry.
Somehow water is coming down within cable inside of
mast or is a result of condensation. Shook water
drops from cable repeatedly, until, by end
of visit, cable was not dripping as much.
Tested #104 after blowing water out of connector.
#104 works, but left 704 in.
After these fixes, prop starting working - so it appears
the prop vane's problem was due to water in the sbus
cable.
Lowered mast to check for source of water entry, found
nothing obvious. Did not remove cable from mast. Raised mast.
From the sonic w and prop Spd data it appears the mast was lowered
at about 18:10 CDT and raised at 18:55.
Note (7/17/02): Looks more like 1815 - 1850 CDT. TWH
Shot angles with KVH data scope. See entries #75,76
Left site at 19:30
72: Site_visit, Site 3, Thu 16-May-2002 09:41:46 CDT, Site 3 visit, May 12
Arrived 12:50, CDT
Attached eve box ground strap
downloaded metppfs to panasonic
cleaned radiometers
cleaned krypton:
before: 657 mV, 10.35 gm/m^3
after: 779 mV, 9.45
checked logger coefficients, two were wrong, see entry #73
took trime soil moisture readings,
TWH note (7/18/02): Gordon forgot to enter the Trime measurements in
the logbook. Here they are from his field notes:
%vol TDR
3.9 57
2.7 59
4.4 55
took photos of site, including CU flux station
left 13:50
71: Site_visit, Site 1, Thu 16-May-2002 09:33:54 CDT, High rate archive at stn 1, May 12
Morning of May 12, site visit to station 1:
These are the microdrives at station 1:
#2 XHAN4374 05B cleared, in eve box
#3 XHAZ2739 09B cleared, in eve box
#4 XHA75885 99B inserted in SDR
Drove to ISS site, and back to stn1 with Bill Brown.
Showed Bill how to swap microdrives.
The archive at stn1 is 40 Mbyte/day, so we can get
a week on a 340 Mbyte microdrive. Asked Bill to
do the swap on Saturdays
df -H reports the microdrives at 358 Mbyte (M=1000000, not 1024x1024)
63: Site_visit, Site 9, Tue 14-May-2002 09:26:10 CDT, Site 9 visit
Gordon and I visited site 9 from about 1830 - 2030 CDT to work on
the kh2o. I cleaned the radiometers and Gordon downloaded the local
data storage.
61: Site_visit, Site 1, Mon 13-May-2002 15:05:48 CDT, Site 1 visit
Site 1 visit, May 11 John and Gordon
Lowered mast to swap everest.
Swapped in new everest, no change. Tried new cable, no change.
Problem of bad Tsfc was actually the slow ad. It was running,
but all quantities, Tsfc, Plicor, Tlicor, Qlicor were constant,
bad values.
After cycling power on slow ad the data came back. Will
watch it tonight and perhaps swap in a new a/d tomorrow
morning.
Swapped in new krypton: 1395 to replace 1101:
1101: 1.31V, -6.09 gm/m^3
1395 0.375, 13.3 gm/m^2
Shot boom angles with KVH (7.5 E declination)
sonic 268.8
prop 177 Old BD was 184, changed it to 177! 7 degrees different!
(Note original sonic direction was 99+180=279, 10 deg different.
This suggests that the original angles were magnetic. TWH)
rad stand 93.4
checked rad coefficients:
One wrong coefficient:
KZ-940186 PSPIN 04 was 80.257, changed to 82.988
(also coefficient 53)
(See logbook entry 14 for pre-project coefficients. TWH)
installed new krypton cal
downloaded slow data
downloaded fast data from SDR microdrive
Fast data files were being created every 1/2 hour.
John fixed SDR config so that file creation is under control of EVE,
not SDR:
entersys, talk to SDR
CR gives menu
#7 File system options
#8 set file closure schedule set it to NO
swapped SDR microdrive
trim readings:
%vol TDR
8.6 48 loose (plowed - actually spaded)
18.6 36 packed (not plowed)
11.3 42 loose (plowed - actually spaded)
TWH: It appears from the sonic data that the mast was lowered
from 23:20 - 23:55 GMT.
57: Site_visit, Site 2, Mon 13-May-2002 14:41:16 CDT, Site 2 visit
arrived about 16:00 CDT John and Gordon
First worked on CSAT/serializer, which has not been reporting. See entry #58
cleaned Rlw.in, Rsw.in, Rpar, Rnet with Kimwipe & distilled H2O
domes looked quite clean beforehand
cleaned krypton with qtip & distilled H2O.
Voltage before: 350mV, after: 670 mV
checked logger coefficients, all correct. See entry #59
installed ground strap on eve box
downloaded slow data
Power monitor system: old version=IHOP_AD.ALT
Vbatt OK at 13 V
eve showing Icharge=249, Iload=.3
Meter at end of cable: Icharge=30-60 mV, Iload=11-12mV
Saw negative voltage on eve front panel. Looks like front
panel has a problem Trust Vbatt, not Icharge, possibly Iload OK
Trime: took 4 readings. See entry #60
Left 17:30
|