Perform SMA radar modifications and training (spring 2003).
Install and conduct limited operation of 3 UHF profilers (June-July 2003)
and routine operations of modified SMA radars (June- Sept 2003).
Evaluation of UHF and SMA radar data, (Fall-winter, 2003-4)
Installation of ISSs, UHF profilers for VISS sites, and 10 cm radar
(spring 2004)
Field phase: a six-to-eight week operation (July-August) of ISSs and VISS
sites (sounding frequency @ six per day during IOPs, twice per day
otherwise, average 4/day) 24/7 operations of polarimetric radar. 50 day
operation for the R/V Brown.
Conduct QC and archival of sounding, profiling and radar data continually throughout
and immediately following operational periods ( NCAR/EOL, NCAR/ATD,
NOAA/AL/ETL, as appropriate).