| Entry | Date | Title | Site | Author | #Graphics | 
|---|---|---|---|---|---|
| 111 | Mon 07-Jan-2002 | Visit 01/04/2002 Task CheckList Review | all stns | militzer | |
| 109 | Fri 04-Jan-2002 | guy wire tension update | tower | militzer | |
| 93 | Tue 18-Dec-2001 | guy wire tension | tower | oncley | |
| 74 | Sat 08-Dec-2001 | staked rad cable | stn2 | oncley | |
| 55 | Thu 06-Dec-2001 | guy wire tension | tower | oncley | 
====================================================================
			FLOSS Service Visit Tasks
				4-Jan.-02
====================================================================
TASKS:
Done: - Site First:
	Place stool under Snow Depth Gauge SR50 while there.
	Later on checked and exposed thermocouple to atmosphere.
Done: - Tower Guy Wire Tension check
	(update logbook entry 55)
	Confirm they are consistent before climbing...
	(alert Kurt if change by more than 50 lbs)
Done: - Tower Thermocouples
	Install 6-each Thermocouples
	Retrieve dead Thermocouples on lower levels
Done: - Tower Photographs
	near top of tower
	See sample photographs with camera.
Done: - Tower 20m Prop Change/Fix dead
Done: - Tower Clean Kryptons	 (alcohol / Q-tips)
Done: - Tower	Clean Radiometers (dry wipes)
Done: - Tower Cal-Gas
	Change 2 cylinders  (update logbook entry 33)
	check flow rate at CO2 sensor inlet
NOT: 	(create logbook entry on flow rate)
NOT:	check	turn on/off:	'ttl_on cosmos 1'
				'ttl_on cosmos 0'
Done: - Tower Precip Gauge fluid level check
	(drain if within 6" top of the gauge)
Done: - PAMs	Clean Kryptons	 (alcohol / Q-tips)
Done: - PAMs	Clean Radiometers (dry wipes)
NOT:  - PAMs	Find/Retrieve Prototype EVE Power Supply
	Could not find this power supply...bummer...
NOT:  - PAM	Bare site Vbatt monitor bad
	Take replacement bbox next time
NOT:  - Trime soil moisture reading; each site
	(update logbook entry 63)
        Battery dead; recharge and take next time.
Done: - Gravimetric soil sample at each site
	(logbook entry 52; clone logbook entry 62)
Done: - Base	Swap backup disk in aster
	Reboot / Check aster
Done: - Base	Retrieve Licor Manual
Done: - Base	Update LOGBOOK
Done: *** DON'T FORGET: REMOVE STOOL FROM UNDER SR50 ***
Guy wire tensions Update
Note: I re-arranged the listing to hopefully make it easier
to track the slackening.
UpDate	 North-East	 South-East	 South-West	 North-West
	 L    M    H	 L    M    H	 L    M    H	 L    M    H
120601	520  650  550,	690  620  480,	620  450  670,	620  490  630
120901	510  650  550,	670  590  480,	560  430  660,	600  480  600
121801	500  600  520,	630  550  440,	570  400  590,	600  475  600
010402	460  540  490,	580  520  400,	540  370  570,	575  440  590
011702	460  550  450,  590  500  390,  570  370  600,  590  450  590
021802  370  470  400,  470  430  410,  480  330  520,  470  350  510
022102  390  550  400,  500  450  350,  510  330  540,  470  360  510
Tony Delany adjusted tensions, see logbook # 151, 21 Feb''02
        660  540  470,  500  410  540,  550  580  480,  450  420  620
022702  690  550  450,  520  430  480,  600  570  470,  560  440  640
Guy wire tensions Updated: lower middle upper NE 520 650 550 SE 690 620 480 SW 620 450 670 NW 620 490 630 This was in about 6 m/s winds from the SW. (The forcast is for very strong winds (50 mph?) today, so I thought I should check.) Update: 9 Dec: NE 510 650 550 SE 670 590 480 SW 560 430 660 NW 600 480 600 (within 20 of the 6 Dec readings). Winds about 4 m/s from the S. Update: 18 Dec: L M H NE 500 600 520 SE 630 550 440 SW 570 400 590 NW 600 475 600
I just put the rad cable up on fence posts. I'm now declaring this site critter-proof. (Ha!)
I just measured guy wire tension: lower middle upper NE 520 650 550 SE 690 620 480 SW 620 450 670 NW 620 490 630 This was in about 6 m/s winds from the SW. (The forcast is for very strong winds (50 mph?) today, so I thought I should check.) Update: 9 Dec: NE 510 650 550 SE 670 590 480 SW 560 430 660 NW 600 480 600 (within 20 of the 6 Dec readings). Winds about 4 m/s from the S.